Corrective actions and change requests MCQs – Software Project Management
1. What is a corrective action in project management?
A) A proactive measure to avoid potential problems
B) A reactive measure to address deviations from the project plan
C) A change request to modify project scope
D) A preventive action to manage risks
Answer: B) A reactive measure to address deviations from the project plan
2. Which document typically includes details on how to implement corrective actions?
A) Project Charter
B) Change Request Form
C) Corrective Action Plan
D) Risk Register
Answer: C) Corrective Action Plan
3. What is a change request in the context of software project management?
A) A formal proposal to modify the project scope, budget, or schedule
B) A notification of a project risk
C) A document outlining the project’s initial requirements
D) A report on project performance
Answer: A) A formal proposal to modify the project scope, budget, or schedule
4. Who is typically responsible for reviewing and approving change requests?
A) Project Manager
B) Project Sponsor
C) Change Control Board (CCB)
D) Development Team
Answer: C) Change Control Board (CCB)
5. What is the purpose of implementing corrective actions?
A) To prevent issues from occurring
B) To address and correct identified issues or deviations
C) To reallocate project resources
D) To develop project requirements
Answer: B) To address and correct identified issues or deviations
6. What should be included in a change request form?
A) Description of the proposed change, impact analysis, and justification
B) Project timeline and budget details
C) Risk assessment and mitigation plan
D) Team member roles and responsibilities
Answer: A) Description of the proposed change, impact analysis, and justification
7. Which process involves identifying, documenting, and addressing deviations in a project?
A) Risk Management
B) Change Management
C) Quality Management
D) Communication Management
Answer: B) Change Management
8. What is the primary objective of the Change Control Board (CCB)?
A) To review and approve or reject change requests
B) To develop the project schedule
C) To allocate project resources
D) To define project scope
Answer: A) To review and approve or reject change requests
9. When should a change request be submitted?
A) At the start of the project
B) When there is a deviation from the project plan or a need for scope modification
C) After project completion
D) During the risk management process
Answer: B) When there is a deviation from the project plan or a need for scope modification
10. Which of the following is NOT a typical reason for a change request?
A) Changes in project scope
B) Project performance issues
C) Adding new requirements
D) Project team building activities
Answer: D) Project team building activities
11. What should be done if a corrective action is not effective?
A) Implement additional corrective actions
B) Ignore the issue
C) Cancel the project
D) Reassess project goals
Answer: A) Implement additional corrective actions
12. Which process involves formally requesting and documenting changes in a project?
A) Integration Management
B) Change Management
C) Schedule Management
D) Scope Management
Answer: B) Change Management
13. What is the role of the Project Manager in managing corrective actions?
A) To implement corrective actions
B) To review and approve change requests
C) To identify issues and initiate corrective actions
D) To develop project requirements
Answer: C) To identify issues and initiate corrective actions
14. What is the key difference between preventive actions and corrective actions?
A) Preventive actions address future risks, while corrective actions address current issues
B) Preventive actions are reactive, while corrective actions are proactive
C) Preventive actions involve cost control, while corrective actions involve schedule changes
D) Preventive actions are used in scope management, while corrective actions are used in risk management
Answer: A) Preventive actions address future risks, while corrective actions address current issues
15. Which document helps in tracking the implementation of corrective actions?
A) Corrective Action Log
B) Project Charter
C) Risk Management Plan
D) Communication Plan
Answer: A) Corrective Action Log
16. What is an impact analysis in the context of change requests?
A) The process of evaluating how a proposed change will affect the project’s scope, schedule, and budget
B) The review of project risks
C) The assessment of project quality
D) The development of project requirements
Answer: A) The process of evaluating how a proposed change will affect the project’s scope, schedule, and budget
17. Which of the following is a typical step in the change management process?
A) Identifying potential risks
B) Documenting and submitting a change request
C) Allocating project resources
D) Developing a project charter
Answer: B) Documenting and submitting a change request
18. What is the purpose of a Corrective Action Plan?
A) To document the plan for addressing project deviations and issues
B) To outline the project’s scope and objectives
C) To track project risks and mitigation strategies
D) To define the project schedule
Answer: A) To document the plan for addressing project deviations and issues
19. Which role is responsible for approving the implementation of corrective actions?
A) Project Team
B) Project Sponsor
C) Project Manager
D) Change Control Board (CCB)
Answer: D) Change Control Board (CCB)
20. What should be done if a change request is approved?
A) Implement the change as per the approval
B) Ignore the request
C) Update the project charter
D) Reassess project risks
Answer: A) Implement the change as per the approval
21. Which process ensures that changes to the project are controlled and managed effectively?
A) Integration Management
B) Change Control
C) Scope Management
D) Risk Management
Answer: B) Change Control
22. What is a primary reason for requesting a change in a project?
A) To address unforeseen issues or new requirements
B) To maintain the project schedule
C) To allocate additional resources
D) To define the project’s initial scope
Answer: A) To address unforeseen issues or new requirements
23. Which of the following is NOT a part of the corrective action process?
A) Identifying issues
B) Developing a risk management plan
C) Implementing corrective actions
D) Monitoring the effectiveness of corrective actions
Answer: B) Developing a risk management plan
24. How should changes be communicated to project stakeholders?
A) Through a formal change request and communication plan
B) Verbally during meetings
C) Through email only
D) By updating the project schedule
Answer: A) Through a formal change request and communication plan
25. What is the purpose of a Change Control Board (CCB)?
A) To approve or reject proposed changes
B) To develop project requirements
C) To track project risks
D) To allocate project resources
Answer: A) To approve or reject proposed changes
26. What should be done before implementing a corrective action?
A) Perform an impact analysis and obtain approval
B) Start executing the action immediately
C) Ignore the deviation
D) Reallocate project resources
Answer: A) Perform an impact analysis and obtain approval
27. Which type of change request involves modifying project scope?
A) Scope Change Request
B) Schedule Change Request
C) Cost Change Request
D) Resource Change Request
Answer: A) Scope Change Request
28. What is the purpose of documenting a change request?
A) To create a formal record of the proposed change and its justification
B) To update the project schedule
C) To allocate additional resources
D) To define project requirements
Answer: A) To create a formal record of the proposed change and its justification
29. Which tool is commonly used to track and manage change requests?
A) Change Log
B) Risk Register
C) Issue Log
D) Corrective Action Plan
Answer: A) Change Log
30. What is the role of the Project Sponsor in change management?
A) To provide final approval for significant changes
B) To implement corrective actions
C) To develop the project schedule
D) To track project performance
Answer: A) To provide final approval for significant changes
31. When should a corrective action be reviewed for effectiveness?
A) After implementation
B) Before implementation
C) During project planning
D) At project initiation
Answer: A) After implementation
32. Which document outlines the need and justification for a change in a project?
A) Change Request Form
B) Risk Register
C) Corrective Action Plan
D) Project Charter
Answer: A) Change Request Form
33. Which of the following best describes a preventive action?
A) A measure taken to avoid future issues
B) A reaction to current project problems
C) A request to modify project scope
D) A review of project performance
Answer: A) A measure taken to avoid future issues
34. What is an essential component of a corrective action plan?
A) Steps for implementation and monitoring
B) Project schedule
C) Risk assessment
D) Project budget
Answer: A) Steps for implementation and monitoring
35. What does a change request usually require before being approved?
A) Evaluation of the impact on project scope, schedule, and budget
B) Reallocation of project resources
C) Updating of project scope
D) Development of new project requirements
Answer: A) Evaluation of the impact on project scope, schedule, and budget
36. How is project performance evaluated for corrective action?
A) By comparing actual performance against the project plan
B) By tracking resource allocation
C) By analyzing project risks
D) By reviewing the project schedule
Answer: A) By comparing actual performance against the project plan
37. What is the first step in implementing corrective actions?
A) Identifying the deviation from the project plan
B) Creating a risk management plan
C) Assigning resources
D) Developing the project schedule
Answer: A) Identifying the deviation from the project plan
38. What should be done after corrective actions are implemented?
A) Monitor the project to ensure the action was effective
B) Allocate additional resources
C) Reassess project goals
D) Update the project scope
Answer: A) Monitor the project to ensure the action was effective
39. What does a corrective action focus on in terms of project performance?
A) Addressing deviations from the project plan
B) Preventing future issues
C) Allocating more resources
D) Defining project scope
Answer: A) Addressing deviations from the project plan
Related Posts:
- Change management and control MCQs - Software Project Management
- Project management software MCQs - Software Project Management(JIRA, MS Project, Trello)
- Using Actions and Batch processing MCQs
- Which of the following is the first event of the asp.net page, when the user requests a web page?
- CI/CD for ASP.NET apps using Azure or GitHub Actions MCQs ASP.NET
- Software Project Management -Components Of Software Project Management: