1. : Each iteration in the incremental model passes through the:
(A) Communication and modeling phases
(B) Planning and construction phases
(C) Deployment and maintenance phases
(D) All phases
2. : PSP activity isolates requirements and size and resource estimates are part of?
(A) Planning
(B) High-level design
(C) High-level design review
(D) Development
3. : In TSP, the sequence of tasks, i.e., scripts, enables the team to establish a solid basis for starting a project in framework activity:
(A) Launch
(B) High-level design
(C) Implementation
(D) Postmortem
4. : Regression testing is a major part of which of the life cycle?
(A) Waterfall model
(B) V model
(C) Iterative model
(D) All of the above
5. : What is the full form of SDLC?
(A) System Design Life cycle
(B) Software Design Life Cycle
(C) System Development Life Cycle
(D) Software Development Life Cycle
6. : In a university, students are asked to develop software. Which model would be preferable?
(A) Waterfall model
(B) Spiral model
(C) Agile model
(D) Code and fix model
7. : Which activity is carried out first?
(A) Verification
(B) Validation
(C) Both
(D) None
8. : What is the advantage of the recursive approach over an iterative approach?
(A) Consumes less memory
(B) Less code and easy to implement
(C) Consumes more memory
(D) More code has to be written
9. : An individual who plans and directs the work is:
(A) Stakeholder
(B) Project manager
(C) Team leader
(D) Programmer